County to Review Moose-Wilson Pathway Engagement Letter
Commissioners are set to review outgoing correspondence asking for meaningful engagement on the Moose-Wilson Corridor Record of Decision Amendment.
Teton County commissioners are set to consider outgoing correspondence titled “Request for Meaningful Engagement on the Moose-Wilson Corridor Record of Decision Amendment” at their Nov. 16 voucher meeting agenda. The agenda does not print the letter text, but the item follows the county’s October letter objecting to the National Park Service’s Aug. 14 amendment, which added a separated multiuse pathway along the full Moose-Wilson corridor and realigned a road segment October letter. For working land on the park edge, the meaningful part is not a slogan. It is whether local agencies get in before a corridor decision is already made.
The record shows commissioners first reviewed a Moose-Wilson draft letter on Sept. 28, when Public Works Project Manager Chris Colligan presented it and eight people gave public comment Sept. 28 minutes. On Oct. 5, the board approved a letter to Interior Secretary Doug Burgum, all in favor, after deleting language reaffirming the county’s 2016 position and deleting a request to consider the county’s 2016 comments Oct. 5 minutes.
Background
The Moose-Wilson Corridor ROD Amendment (2026) adds a full-corridor multiuse pathway and road realignment, prompting Teton County to review outgoing correspondence seeking greater local involvement.
Latest: 2026-10-05 — Board submits letter to the Secretary of the Interior requesting reconsideration and greater engagement.
curated as of 2026-11-14
Teton County's Board opposed a corridor-length pathway in the National Elk Refuge Bison and Elk Management Plan DEIS, citing wildlife and process concerns, and called for alternatives and better local engagement (2025–2026).
Latest: 2026-07-07 — Board reiterated its DEIS concerns and recommendations in a formal objection letter regarding the Final Environmental Impact Statement (FEIS) and draft Record of Decision, referencing the original June 2025 comments.
curated as of 2026-10-10
In 2026, Teton County opposed the addition of a separated multiuse pathway to the Moose-Wilson Corridor plan, requested reconsideration, and formally sought cooperating agency status to influence federal planning.
Latest: 2026-10-05 — Teton County formally requested inclusion as a cooperating agency in the federal planning process for the Moose-Wilson Corridor.
curated as of 2026-10-04