Meeting:

Planning Commission to review Suzanne Lagerman conditional use permit for Hoback Junction water plant

On Nov. 9, the Planning Commission is set to consider Suzanne Lagerman’s conditional use permit application for a Hoback Junction Water and Sewer District utility facility, with staff recommending approval and in-river timing and screening conditions.

The Teton County Planning Commission is set to review a conditional use permit request from Suzanne Lagerman of Nelson Engineering for a Hoback Junction Water and Sewer District utility facility that would build a new public water supply, treatment, distribution, and storage system for the district agenda. Staff describe the district as formed in 2023 in response to high nitrate levels in private drinking water sources, and the project as including a Snake River infiltration gallery and a 420 square foot treatment building, plus distribution lines and storage staff packet. The planning director recommends approval of the conditional use permit with two conditions, one limiting in-river work to low flow months and outside the March 15 to July 31 cutthroat trout spawning window, and one requiring landscape screening between the facility and the river corridor staff packet. The record shows no written public comments had been received as of the staff report staff packet.

The prior record on this project shows the county commissioners voted Sept. 1 to waive about $13,488 in county permit fees for the district’s water system improvements minutes, after staff estimated the full waiver request at about $13,616 across planning, building, engineering, and fire permits fee waiver staff report.

If this moves forward, the practical schedule question is whether the low flow, no-spawning-season constraint lines up with the district’s construction calendar this winter.

Background

Hoback Junction Water & Sewer District Conditional Use Permit

Suzanne Lagerman submitted CUP2026-0004 for a Hoback Junction water facility, reviewed Nov. 9, 2026, with detailed environmental and zoning requirements; project cost not disclosed.

Latest: 2026-11-09 — Teton County Planning Commission considered CUP2026-0004 for the Hoback Junction Water & Sewer District utility facility submitted by Suzanne Lagerman.

curated as of 2026-11-06

Variance Request for Water Treatment Facility in Teton County

Suzanne Lagerman requested a variance to reduce the side setback for a water treatment facility from 10 ft to 3 ft; the request was considered on November 9, 2026, but the outcome is not yet documented.

Latest: 2026-11-09 — Suzanne Lagerman's variance request (VAR2026-0003) to reduce the side setback from 10 ft to 3 ft for the Hoback Junction Water & Sewer District utility facility was considered by the Teton County Planning Commission.

curated as of 2026-11-04

Hoback Junction Wastewater Feasibility Study

The Hoback Junction Wastewater Feasibility Study began in 2025 with a broad assessment scope; in 2026, the District sought expanded funding and scope, with formal Board discussion on expansion by October 2026.

Latest: 2026-10-16 — Water Quality Advisory Board agenda included discussion of expanded scope for Hoback Junction Wastewater Feasibility Study.

curated as of 2026-10-14

Source Documents

DateTitleType
November 9, 2026Planning Commission Meeting Agendaagenda
November 9, 2026Planning Commission Meeting Packet — Hoback Junction Water and Sewer District Utility Facility and Variancepacket
October 6, 2026Regular Meeting Minutesminutes
September 1, 2026MSC Staff Report — Hoback Water & Sewer District Fee Waiver Requeststaff report