Justice Center report to commissioners holds budget at $118.5 million as cushion shrinks

The October monthly report going to Teton County commissioners says the Justice Center is on budget at $118.5 million. Owner contingency has slipped to $2.83 million, and several large pending change items are still unpriced.

Teton County commissioners will receive the Justice Center's October monthly report today. Project managers Wember and Berning Project Management report that the $118.5 million budget, "which includes all soft costs and contingencies," is still on budget (October update). The accounting table now totals $118,550,000. The extra $50,000 is the public art budget increase that Jackson Hole Public Art committed to cover. Committed costs stand at $110.7 million and incurred costs at $33.1 million. Owner contingency, counting pending costs, is down to $2,833,113.73. That splits into $998,794.73 of construction contingency and $1,834,319 of escalation contingency. Several large items remain pending: a $449,012 clean agent fire protection system for the Sheriff's IT room, a $250,000 security backup power system with "final pricing TBD," a $219,888 passive radon system, and a $140,000 architect construction administration amendment marked "waiting for AIA Document." The fire and backup power items depend on pending transfers from the technology budget. The report lists unknown escalation costs as a risk.

The August 31 report put contingency at $3,048,798.60, and construction incurred costs at $21.2 million (August update). The July report showed $2,973,167.72 (July update). Both reports date the budget to the final guaranteed maximum price that commissioners approved February 17, 2026. The project still carries 26 months of construction ahead of a December 2028 finish, and the "on budget" claim now rests partly on moving technology money into contingency.

Background

Teton County Justice Center Project

ASR-010, approved May 5, 2026, added $140,000 in architectural services for the Teton County Justice Center, expanding scope and schedule but not the $118.5M project budget.

Latest: 2026-09-01 — Project updates confirm expanded scope (third courtroom, new support spaces) and increased facility size to 80,120 sq ft, all within the $118.5M budget.

curated as of 2026-09-01

Teton County Fiscal Year 2027 Budget Approval

Teton County Board unanimously approved the FY2027 budget on July 21, 2026, with notable changes in staffing, fund structure, and allocations, but the total budget amount is not specified in available records.

Latest: 2026-07-21 — Teton County Board unanimously approved the FY2027 budget at a special meeting.

curated as of 2026-07-21

Teton County Public Budget Hearing

Teton County's FY 2026-2027 budget hearing is June 29, 2026, with adoption set for June 30. Major projects include wildfire mitigation, park upgrades, housing, and transportation improvements.

Latest: 2026-06-30 — County Commission scheduled to adopt the final FY 2026-2027 budget.

curated as of 2026-06-27

Source Documents

DateTitleType
October 5, 2026BCC Staff Report — Wember BPM Updatesstaff report
August 31, 2026Teton County Justice Center Staff Report — Wember BPM Updatesstaff report
July 6, 2026Teton County Justice Center Wember Report Staff Reportstaff report