Town, county to settle $19,860 gap over who pays to run the pathways

Jackson Town Council and Teton County commissioners meet Monday to choose a cost split for the $331,001 pathways operating budget. The county wants 54/46 and the town wants 60/40, a gap of $19,860.

The pathways program costs $331,001 a year to run in fiscal 2027. That budget pays for the people and work behind the paved network between town and the trailheads: "staff salaries, programming, safety education, professional services, system management, planning" and development review, according to the joint meeting packet. Mowing, plowing and paving are budgeted elsewhere. On Monday, Oct. 5, the Jackson Town Council and Teton County commissioners are set to pick a split. The county has proposed 54% county and 46% town, which comes to $178,740 and $152,260. The town wants to keep the current 60/40 split: $198,600 from the county and $132,400 from the town. The packet puts the gap at $19,860, and staff "have not made a joint or individual recommendation."

The September 14 packet traces the history. The 2003 pathways agreement split operations 50/50. In 2011 the split moved to the census-based 54/46. A 2024 joint funding agreement then phased in 60/40 for this year and 62/38 for fiscal 2028. The boards did not agree on this line at that meeting. They did agree that pathways capital projects stay with whichever jurisdiction the project sits in. Over the past five years that has meant the county paid 93% of capital costs. For the program that plans every new connector, the fight is about less than $20,000 a year, a small sum next to the capital bills.

Background

Pathways Operating Funding Split

FY27 Pathways Operating expenses are $331,001, split 60% County and 40% Town per the Joint Funding MOU, with a planned shift to 62/38 in FY28.

Latest: 2027 — Planned shift to a 62% County / 38% Town split for Pathways Operating in FY28.

curated as of 2026-10-04

Pathways Capital Funding Split in Teton County, Wyoming

Town and County will decide the Pathways Capital funding split at their October 5, 2026 joint meeting, considering several split options for the $18.1M project.

Latest: 2026-10-05 — Scheduled joint meeting to finalize the Pathways Capital funding split, with options including Census Split (54%/46%), phased MOU splits (up to 62%/38%), and continued jurisdictional split.

curated as of 2026-10-02

Teton County Parks and Recreation Funding Scenarios

Town and County will discuss alternative Parks & Rec funding, including a 56% Town/44% County split, at a joint meeting on July 6, 2026.

Latest: 2026-07-06 — Town and County scheduled to discuss alternative funding scenarios, including the 56% Town/44% County split, at a joint meeting.

curated as of 2026-07-05

Source Documents

DateTitleType
October 5, 2026Parks and Recreation Joint Powers Agreement Review Packetpacket
September 14, 2026Parks and Recreation Joint Powers Agreement Review Packetpacket