Coroner facility seasonal housing is pegged at $600,000 to $1,000,000

A county staff report put the add-on cost for seasonal housing above the new Coroner’s Facility at $600,000 to $1,000,000, a reminder that even “small” housing adds up fast in Jackson.

Teton County staff told commissioners the current construction estimate to add seasonal housing on a second floor above the new Coroner’s Facility is between $600,000 and $1,000,000 staff report.

As a parent, I read that as the price tag for one extra housing unit tied to a public-safety facility. It is also a glimpse of why it is so hard to build any workforce housing here, even when the county is already pouring a foundation for something else. The same staff report notes the project has $1,000,000 budgeted in FY27, with staff saying more design work on second-floor options would not significantly affect a potential construction start next year. (The estimate is still a range, and the final design and capacity for the housing piece have not been locked in yet.)

Background

Teton County Coroner's Facility Seasonal Housing

Seasonal housing in the Coroner's Facility is estimated at $600,000–$1,000,000 extra, with construction planned for FY27–FY28.

Latest: 2028-06 — FY28 ends; anticipated construction completion for seasonal housing.

curated as of 2026-09-18

Coroner Facility Design Contract in Teton County

On September 1, 2026, the Teton County Commission approved adding seasonal employee housing to the Coroner Facility project, increasing design fees by $61,000 and construction costs by $588,800–$1,030,400.

Latest: 2026-09-01 — Commission formally approves $61,000 fee for Plan One/Architects to incorporate housing into the Coroner Facility design; estimated construction cost increase for housing is $588,800–$1,030,400.

curated as of 2026-08-29

Coroner's Facility at Adams Canyon

Plan One Architects was awarded a $326,248 contract in February 2026 to design Teton County's new Coroner's Facility at Adams Canyon, with phased milestones and potential for added employee housing.

Latest: 2027-03 to 2027-12 — Construction phase for Coroner's Facility.