County locks in Gros Ventre Road snow removal at $100,832 for year one
Commissioners approved Ridgeline Excavation’s 2026-2031 Gros Ventre Road snow removal contract, $100,832.36 for the first season, then indexed annually for inflation.
Teton County commissioners approved a 2026-2031 Gros Ventre Road Snow Removal Project contract to Ridgeline Excavation, Inc. for $100,832.36 for the first season, with later years adjusted by the Wyoming Cost of Living Index commission minutes.
The staff report describes it as a five-year, annual-performance contract covering a 3.75-mile segment plus “four paved parking areas” and the Atherton Campground entrance/parking. The county says it negotiated a 0% increase from last winter because Ridgeline was the sole bidder and other contractors showed little interest, and it concluded doing the work in-house would require expensive equipment, storage space, and hard-to-hire operators snow removal contract packet.
Background
Teton County approved a five-year, $504,161.80 (base) contract with Ridgeline Excavation, Inc. for Gros Ventre Road snow removal, with annual cost of living adjustments and standard contract terms.
Latest: 2027-2031 — Subsequent years of the contract, with annual price adjustments based on the Wyoming Cost of Living Index.
curated as of 2026-09-03
The 2026-2027 snow removal contract with Ridgeline Excavation, Inc. was approved at $103,983.38, with no price increase from the previous year, as part of a five-year agreement.
Latest: 2026-08-04 — Teton County Board of County Commissioners officially approves the 2026-2027 snow removal contract with Ridgeline Excavation, Inc. at the same price as the previous year, with zero-percent increase.
curated as of 2026-08-04
Teton County approved a five-year, inflation-adjusted contract with Ridgeline Excavation, Inc. for North Jackson snow removal, starting at $86,337.71 in year one, on August 4, 2026.
Latest: 2026-08-04 — Board of Commissioners approved five-year contract for North Jackson Snow Removal Project with Ridgeline Excavation, Inc. First-year cost set at $86,337.71.
curated as of 2026-08-04
Source Documents
| Date | Title | Type |
|---|---|---|
| September 1, 2026 | Commission Meeting Minutes | minutes |
| August 4, 2026 | BCC Packet — Gros Ventre Road Snow Removal Project Contract | packet |