County commissioners approve $140,000 Justice Center architect fee
Teton County approved ASR-010 for Anderson Mason Dale Architects, adding $140,000 for extended Justice Center construction administration tied to the project’s expanded courtroom and support-space scope.
Teton County commissioners approved Additional Services Request ASR-010 for Anderson Mason Dale Architects, a $140,000 contract amendment for the Justice Center project. The staff report says the extra fee covers extended construction administration after the project picked up a third courtroom, a multi-functional Municipal Court and jury assembly space, a Victims Services suite, and a small jail administrative suite with staff locker rooms. BCC Staff Report, Additional Services Request by Anderson Mason Dale Architects
The county says the added work comes out of the Justice Center owner’s contingency budget, not a bigger overall project budget. The report ties the request to a construction timeline that now runs from February 2026 through November 2028, about 17 weeks longer than originally planned. That is the kind of change workers notice when a public project grows but the county tries to keep the sticker price flat.
Source Documents
| Date | Title | Type |
|---|---|---|
| September 1, 2026 | BCC Staff Report — Additional Services Request by Anderson Mason Dale Architects | staff report |