County locks in $103,983 South Jackson snow removal deal with Ridgeline
Teton County commissioners approved a five-year South Jackson snow removal and sanding contract with Ridgeline Excavation starting at $103,983.38 for the first year, with later years tied to the Wyoming cost of living index.
Teton County locked in its next South Jackson plowing and sanding contract at $103,983.38 for the first year, approving a 2026-2031 agreement with Ridgeline Excavation, Inc. for the South Jackson Snow Removal Project staff report and contract.
For commuters, the practical piece is stability: the county is keeping the same contractor in place for another multi-year term, and the agreement sets later-year pricing as a cost-of-living adjustment off the first-year base price. The contract said work would not start until a written Notice to Proceed from the Road and Levee manager, expected “on or about August 15, 2026.”
Background
The 2026-2031 South Jackson Snow Removal Project contract was awarded to Ridgeline Excavation, Inc. for at least $519,916.90 over five years, covering comprehensive snow removal services with annual cost-of-living adjustments.
Latest: 2031-06-30 — Scheduled contract completion date, with option for up to three-year renewal.
curated as of 2026-08-06
Teton County approved a five-year, inflation-adjusted contract with Ridgeline Excavation, Inc. for North Jackson snow removal, starting at $86,337.71 in year one, on August 4, 2026.
Latest: 2026-08-04 — Board of Commissioners approved five-year contract for North Jackson Snow Removal Project with Ridgeline Excavation, Inc. First-year cost set at $86,337.71.
curated as of 2026-08-04
The 2026-2027 snow removal contract with Ridgeline Excavation, Inc. was approved at $103,983.38, with no price increase from the previous year, as part of a five-year agreement.
Latest: 2026-08-04 — Teton County Board of County Commissioners officially approves the 2026-2027 snow removal contract with Ridgeline Excavation, Inc. at the same price as the previous year, with zero-percent increase.
curated as of 2026-08-04
Source Documents
| Date | Title | Type |
|---|---|---|
| August 4, 2026 | South Jackson Snow Removal Project Contract Staff Report and Resolution | packet |