DPR Construction to manage Justice Center build through May/June 2028

County commissioners are set to review a Justice Center update Monday that rebrands contractor GE Johnson Wyoming as DPR Construction and pegs construction completion to May or June 2028.

Teton County commissioners are set to hear a monthly update Monday that puts DPR Construction in the project-manager seat for the Teton County Justice Center, after construction manager GE Johnson Wyoming began operating under the DPR name. The report says that, starting with August’s update, “we will be referring to GE Johnson Wyoming as DPR Construction (DPR)” Justice Center staff report.

The schedule in the same update lists “Construction Completion May/June 2028,” a timeline that sits inside the county’s broader plan to finish the new Justice Center in 2028 after construction began in May 2026. (The county approved the project’s final guaranteed maximum price in February 2026.) Justice Center staff report.

Source Documents

DateTitleType
August 3, 2026Teton County Justice Center Staff Report — Wember Updatesstaff report