AMD proposals would need a $395 pre-application conference

Teton County is considering a required pre-application conference for LDR text amendments, adding a $395 early step meant to improve draft proposals before formal review.

A landowner or resident who wants to propose a county Land Development Regulation text amendment would first have to sit down with planning staff for a pre-application conference, currently priced at $395, under AMD2026-0002. The point, according to the Planning Commission staff report, is to catch weak drafting, technical problems, or conflicts with county priorities before a formal amendment starts consuming hearing time and staff review.

Background

Teton County Planning Commission Review of AMD2026-0002

AMD2026-0002 centralizes initiation of LDR and zoning map amendments to County officials, adds pre-application conferences, lowers fees, and aligns reviews with annual work planning.

Latest: 2026-08-04 — Board of County Commissioners scheduled public hearing for AMD2026-0002.

curated as of 2026-07-09

Teton County Board of County Commissioners Amendment

Teton County considered a process amendment (AMD2026-0002) in spring 2026 to align with new state housing laws, shifting amendment initiation to the Board or Planning Director and streamlining public input.

Latest: 2026-05 — Staff and Planning Director recommend approval of AMD2026-0002, changing the process for LDR and Zoning Map Amendments to be Board/Director-initiated, requiring pre-application conference, and removing the $1,500 application fee.

curated as of 2026-05-30

Teton County Public AMD and ZMA Proposals

AMD2026-0002 gives the Board of County Commissioners exclusive authority to initiate all public AMD and ZMA proposals, ending direct public applications but preserving public input via the Work Plan process.

Latest: 2026-06-01 — AMD2026-0002 amends LDR Sections 8.1.5, 8.7.1, 8.7.2, and 8.10.5 to require that only the BOCC or Planning Director can initiate AMD and ZMA proposals. Public proposals must go through the BOCC for consideration.

curated as of 2026-05-28

Source Documents

DateTitleType
June 1, 2026Planning Commission Staff Report — AMD and ZMA Process Change Applicant Submissionsstaff report