Teton commissioners approve $23,714 fixes for Justice Center temp offices
On March 3, the Teton County Commission approved Change Order 006 for the Justice Center’s temporary offices, a $23,713.99 package largely aimed at freeze protection and electrical code compliance.
Teton County’s Board of County Commissioners approved Change Order 006 for the Justice Center temporary offices project on March 3, authorizing a $23,713.99 package of fixes under the county’s contract with DPR/GE Johnson. The work is tied to the temporary buildings being used while the new Justice Center is built. (See: Justice Center Staff Report.)
According to the staff report, the biggest line items are additional insulation under the temporary facilities to protect drain/waste/vent piping from freezing ($10,436.02), freeze protection for the domestic water connection between two buildings ($4,667.76), and a rough-in for a potential domestic-water pump to address water-pressure concerns ($4,911.75). The change order also includes $1,626.42 for remote GFCI protection to meet electrical code and $2,072.04 in miscellaneous combined costs.
Several other elements in the package are listed at $0 because they are covered by contractor contingency already included in the guaranteed maximum price, including coordination and expedited shipping for electrical gear, rerouting MEPs that conflict with attic conditions, replacing noncompliant exterior emergency lighting, and repairing an existing mechanical unit, the report says. The $23,713.99 cost is funded through a mix of owner contingency and established contractor contingency. (See: Justice Center Staff Report.)
Background
On October 6, 2026, Teton County approved a $668,900 change order for the Justice Center, adding clean agent fire protection and radon mitigation systems to the project.
Latest: 2026-10-06 — Owner Change Order 014 approved by the Board, adding clean agent fire protection and passive radon mitigation systems to the Justice Center project.
curated as of 2026-11-10
Teton County's temporary court building budget rose from $118,649 to $5 million after Change Order #3, which covered all modular court facility costs.
Latest: 2023-09 — Change Order #3 finalized, establishing full modular court facility costs.
curated as of 2026-10-31
Teton County Board unanimously approved the FY2027 budget on July 21, 2026, with notable changes in staffing, fund structure, and allocations, but the total budget amount is not specified in available records.
Latest: 2026-07-21 — Teton County Board unanimously approved the FY2027 budget at a special meeting.
curated as of 2026-07-21
Source Documents
| Date | Title | Type |
|---|---|---|
| March 3, 2026 | Justice Center Staff Report | staff report |