Teton County lets staff approve Justice Center change orders up to $100K

On March 3, Teton County commissioners approved a resolution allowing the general services director to sign Justice Center change orders up to $100,000 each, with a $2 million cap on county-held contingency and bi-monthly reporting back to the board.

Teton County commissioners approved a March 3 resolution delegating limited change-order authority for the Teton County Justice Center to the county’s director of general services. Under the resolution, the director may execute Justice Center change orders that have no fiscal impact, or that draw on county-held construction contingency funds up to $100,000 per change order, as long as the work stays within the project scope and budget and the county-approved total does not exceed $2 million. Larger change orders (over $100,000) must still come back to the Board of County Commissioners for approval.

The resolution also sets a backstop: if the aggregate of change orders signed under this delegated authority reaches $2 million, any additional change orders beyond that threshold must be submitted to commissioners for approval and signature.

Separate from county-held contingency, commissioners also authorized the general services director to approve the contractor’s use of contractor-held contingency identified in the project’s Guaranteed Maximum Price (GMP) contract. Staff told commissioners the resolution covers about $5.1 million in contractor-held contingency/allowances within the GMP and $2 million of the $4.8 million contingency currently held by the county. The resolution requires the director to provide bi-monthly updates to commissioners on the project’s status and what change orders have been signed in each contingency category. See the staff report and adopted resolution in the March 3 packet: Board of Supervisors Staff Report and Resolution Attachment.

Background

Teton County Justice Center Owner Change Order 014

On October 6, 2026, Teton County approved a $668,900 change order for the Justice Center, adding clean agent fire protection and radon mitigation systems to the project.

Latest: 2026-10-06 — Owner Change Order 014 approved by the Board, adding clean agent fire protection and passive radon mitigation systems to the Justice Center project.

curated as of 2026-11-10

Teton County Temporary Court Building Costs

Teton County's temporary court building budget rose from $118,649 to $5 million after Change Order #3, which covered all modular court facility costs.

Latest: 2023-09 — Change Order #3 finalized, establishing full modular court facility costs.

curated as of 2026-10-31

Teton County Fiscal Year 2027 Budget Approval

Teton County Board unanimously approved the FY2027 budget on July 21, 2026, with notable changes in staffing, fund structure, and allocations, but the total budget amount is not specified in available records.

Latest: 2026-07-21 — Teton County Board unanimously approved the FY2027 budget at a special meeting.

curated as of 2026-07-21

Source Documents

DateTitleType
March 3, 2026Board of Supervisors Staff Report and Resolution Attachmentattachment