Teton County picks Whitaker as CMAR for Teton Pass Trail Segment 2

On March 3, 2026, Teton County commissioners were asked to approve a $58,200 CMAR preconstruction contract with Whitaker Construction for the BUILD-grant Teton Pass Trail Segment 2, a project whose final scope depends on capped public funding and ongoing fundraising.

Teton County commissioners on March 3 considered approving a Construction Manager at Risk (CMAR) contract with Whitaker Construction Company for preconstruction services on the BUILD-grant-funded Teton Pass Trail Segment 2. The preconstruction contract totals $58,200, with costs budgeted in the county’s BUILD grant fund and reimbursable by the federal grant up to 80%, according to the county staff report. See: Consideration of Teton Pass Trail Construction Manager at Risk Contract Agreement.

Segment 2 is planned to extend from the Idaho/Wyoming state line at Trail Creek Campground east toward Coal Creek Trailhead (up to about 3.5 miles), creating a separated pathway intended to reduce bike/ped conflicts on a narrow stretch of WY-22 while tying into the larger Greater Yellowstone Trail vision. But because BUILD and county contributions are capped and philanthropy is still being raised, staff said the exact buildable scope is uncertain — a key reason the county opted for CMAR delivery rather than a traditional low-bid contract.

Under the approach described to commissioners, Whitaker would provide constructability reviews, scheduling help and cost estimating leading to a future, publicly bid Guaranteed Maximum Price (GMP) package sized to the funding that’s actually available. County staff reported Whitaker was the top-scoring proposer in a qualifications-based process (94.2/100) and had already received a notice of award Feb. 17. See: CMAR Notice of Award staff memo.

The staff report also frames the trail decision in the context of earlier cost/scope discussions — including a Sept. 29, 2025 commission direction to pursue a reduced-scope agreement revision with the Federal Transit Administration, with the county committing to 20% of total project cost while private fundraising continues. See: October 20, 2025 letter describing funding options and scope.

Background

Teton Pass Trail Project

In 2026, Teton County approved a $794,798.88 CMAR contract and Amendment #1 for the Teton Pass Trail, with 75% reimbursable by the BUILD grant and a 25% local match.

Latest: 2026-05-11 — Board approved Amendment #1 to CMAR Contract, setting Early Work Package GMP at $794,798.88.

curated as of 2026-06-13

FY2020 BUILD Transportation Grants Program in Teton County, Wyoming

On July 7, 2026, Teton County approved a second amended BUILD grant agreement, increasing the total to $25M, updating project scopes, reallocating funds, and extending deadlines for the Teton Mobility Corridor Improvements.

Latest: 2026-07-07 — Second Amended and Restated Grant Agreement approved by Teton County Board of County Commissioners; major project scope and budget changes enacted, deadline extended to December 15, 2027.

curated as of 2026-07-05

Teton Science School Multimodal Tunnel Project

On August 11, 2026, Teton County Commissioners considered a $3,355 fee waiver request from Teton Science School for a multimodal tunnel project under HWY 22; the outcome is not specified in current records.

Latest: 2026-08-11 — Teton County Board of County Commissioners considered the Teton Science School's fee waiver request for the multimodal tunnel project under HWY 22, totaling up to $3,355 in waived fees.

curated as of 2026-08-08

Source Documents

DateTitleType
March 3, 2026Board of County Commissioners Staff Report and Contract Packet — Teton Pass Trail Construction Manager at Risk Agreementpacket
February 17, 2026BCC Meeting Packet — Teton Pass Trail Construction Manager at Risk Notice of Awardstaff report
October 20, 2025Teton County Board of County Commissioners Correspondencecorrespondence