Teton commissioners approve $23,714 change order for Justice Center temp offices

On March 3, the Teton County Board of Commissioners approved Change Order 006 ($23,713.99) for the Justice Center’s temporary modular offices, covering freeze-protection and electrical/code fixes paid from project contingencies.

Teton County commissioners voted March 3 to approve a $23,713.99 change order for the Justice Center project’s temporary offices/modular facilities, a package of fixes aimed largely at winterization and code compliance. The action approved “Change Order 006” with DPR/GE Johnson (now operating as DPR Construction locally), per the county’s staff report. Justice Center Staff Report

According to the staff report, the largest line items were additional freeze protection for the domestic water connection between buildings ($4,667.76), rough-in work for a possible domestic water pump to address water-pressure concerns ($4,911.75), and added insulation under the temporary facilities to protect drain/waste/vent piping ($10,436.02). Other elements were listed as contractor-contingency items at $0 cost to the owner, including electrical panel coordination/expedited shipping, MEP reroutes, replacing non-compliant exterior emergency lighting, and a mechanical unit repair. Justice Center Staff Report

The change order is part of the broader temporary-relocation effort needed while the county replaces the existing courthouse and detention center with the new Justice Center. A separate project update report earlier in March noted preparations for moving courthouse users into the temporary courtrooms/offices and described the effort as part of the overall Justice Center delivery. Project Monthly Update Report

Background

Teton County Justice Center Owner Change Order 014

On October 6, 2026, Teton County approved a $668,900 change order for the Justice Center, adding clean agent fire protection and radon mitigation systems to the project.

Latest: 2026-10-06 — Owner Change Order 014 approved by the Board, adding clean agent fire protection and passive radon mitigation systems to the Justice Center project.

curated as of 2026-11-10

Teton County Temporary Court Building Costs

Teton County's temporary court building budget rose from $118,649 to $5 million after Change Order #3, which covered all modular court facility costs.

Latest: 2023-09 — Change Order #3 finalized, establishing full modular court facility costs.

curated as of 2026-10-31

Coroner Facility Design Contract in Teton County

On September 1, 2026, the Teton County Commission approved adding seasonal employee housing to the Coroner Facility project, increasing design fees by $61,000 and construction costs by $588,800–$1,030,400.

Latest: 2026-09-01 — Commission formally approves $61,000 fee for Plan One/Architects to incorporate housing into the Coroner Facility design; estimated construction cost increase for housing is $588,800–$1,030,400.

curated as of 2026-08-29

Source Documents

DateTitleType
March 3, 2026Justice Center Staff Reportstaff report
March 2, 2026Teton County Justice Center Project Update Packetpacket