Teton County delegates $100K Justice Center change-order signoff to staff

On March 3, county commissioners approved a resolution letting the General Services director sign Justice Center change orders up to $100,000 each (with a $2M aggregate cap) and approve use of contractor-held contingency under the GMP.

Teton County commissioners approved a resolution March 3 authorizing the county’s director of General Services to execute Justice Center change orders of up to $100,000 each, so long as the costs stay within the project’s budget/scope and the total of county-held contingency spent under the delegation does not exceed $2 million. Change orders over $100,000—or any change orders after the $2 million aggregate threshold is reached—must go back to the Board of County Commissioners for approval. (Board of Supervisors Staff Report and Resolution Attachment)

The same resolution also authorizes the General Services director to approve the contractor’s use of contractor-held contingency specified in the project’s guaranteed maximum price (GMP) contract. County staff told commissioners the delegation is intended to speed responses to construction issues and keep timelines moving, with staff required to brief the board on a bi-monthly basis about what change orders were signed and under which contingency category. (Board of Supervisors Staff Report and Resolution Attachment)

In its fiscal impact section, the staff report framed the change-order process around multiple contingency pools: about $5.1 million in contractor-held contingency and allowances within the GMP, plus $2 million of the roughly $4.8 million in contingency the county is holding. A separate staff report in the same March 3 packet recommended approval of a $23,713.99 Justice Center-related change order for temporary offices, with items such as freeze protection and electrical/code adjustments drawing on contractor and owner contingency. (Board of Supervisors Staff Report and Resolution Attachment; Justice Center Staff Report)

Background

Teton County Justice Center Project

ASR-010, approved May 5, 2026, added $140,000 in architectural services for the Teton County Justice Center, expanding scope and schedule but not the $118.5M project budget.

Latest: 2026-09-01 — Project updates confirm expanded scope (third courtroom, new support spaces) and increased facility size to 80,120 sq ft, all within the $118.5M budget.

curated as of 2026-09-01

Teton County Temporary Court Building Costs

Teton County's temporary court building budget rose from $118,649 to $5 million after Change Order #3, which covered all modular court facility costs.

Latest: 2023-09 — Change Order #3 finalized, establishing full modular court facility costs.

curated as of 2026-10-31

Teton County Fiscal Year 2027 Budget Approval

Teton County Board unanimously approved the FY2027 budget on July 21, 2026, with notable changes in staffing, fund structure, and allocations, but the total budget amount is not specified in available records.

Latest: 2026-07-21 — Teton County Board unanimously approved the FY2027 budget at a special meeting.

curated as of 2026-07-21

Source Documents

DateTitleType
March 3, 2026Board of Supervisors Staff Report and Resolution Attachmentattachment
March 3, 2026Justice Center Staff Reportstaff report