Teton County weighs $6.9M remaining Water Quality SPET allocations

At a March 2 workshop, Teton County commissioners reviewed staff/WQAB recommendations for allocating $6.897M in remaining 2022 Water Quality SPET funds, including major sewer and stormwater projects, and gave direction for upcoming funding agreements.

Teton County’s Board of County Commissioners discussed how to allocate the remaining $6.897 million in 2022 Water Quality SPET funds during a March 2 workshop, reviewing staff and Water Quality Advisory Board (WQAB) recommendations across infrastructure, stormwater/nonpoint source mitigation, and monitoring/studies. The workshop was informational and intended to set up direction for drafting individual funding agreements that will return to the board for action.

The staff report’s recommendation package totaled $6.897 million and emphasized infrastructure (about 80% of the remaining funds). The largest single line item was $2 million recommended for the Wilson Sewer District’s Phase 4 sewer project (down from a $3.31 million request), with conditions tied to connection requirements in district rules. Other recommendations included $1.5 million for Town of Jackson stormwater improvements; $317,000 for a county monitoring/feasibility effort; and $1 million toward the Elk Refuge Sewer District’s North Highway 89 sewer project—though the report noted the Elk Refuge request was recommended to be financed via a long-term improvement service district (ISD) loan rather than a SPET grant.

A preliminary schedule tied to projected SPET collections laid out when funds could be available from 2026 through 2029, with staff noting that if the board changes funding amounts, the schedule and agreements would need to be updated. Staff said they anticipate close coordination with sponsors and legal review as the agreements are developed for a future board meeting. (Workshop staff report: Water Quality SPET Funding Proposals)

Background

Teton County Water Quality Management Plan

In June 2026, Teton County allocated $2.83M in 2022 Water Quality SPET funds to three water quality projects, including stormwater and wastewater improvements and a monitoring dashboard.

Latest: 2026-06-16 — Teton County Commissioners adopted a resolution allocating $2,830,000 in SPET funds to three water quality projects: $1.5M to Town of Jackson (stormwater), $1.25M to Elk Refuge Sewer District (wastewater), $80K to Trout Unlimited (monitoring dashboard).

curated as of 2026-07-21

Water Quality SPET Funding Resolution in Teton County

In June 2026, Teton County approved a resolution allocating $2.83M in Water Quality SPET funds to local water quality projects, including stormwater upgrades, sewer improvements, and data monitoring.

Latest: 2026-06-16 — Board of County Commissioners approved a resolution allocating $2,830,000 in remaining Water Quality SPET funds: $1.5M to Jackson stormwater, $1.25M to Elk Refuge Sewer District, $80K to Trout Unlimited.

curated as of 2026-06-19

WSD & North 89 SPET Funding

Teton County allocated $1M in SPET funds for the Elk Refuge SD North 89 Sewer project, with broader water quality improvements and a BCC meeting on July 21, 2026.

Latest: 2029-12 — Scheduled distribution of $1,000,000 SPET funds for North 89 Sewer project.